site logo fixed header logo

North Lake, MBR Treatment Plant

FILTER PROJECTS
project featured image

Cassia County, Yale Road

Cassia County, Idaho
project featured image

Nampa, Autovol

Nampa, Idaho
project featured image

TVWD, Grabhorn Reservoir

Washington County, Oregon
project featured image

Lava Hot Springs, Solar Project

Lava Hot Springs, Idaho
project featured image

MSE Retaining Wall

Gem County, Idaho
project featured image

Hiline Road

Chubbuck, Idaho
project featured image

Harrison Bridge

Kootenai County, Idaho
project featured image

Marshall Racine Trail

Pocatello, Idaho
project featured image

Weiser, River Trail

Adams and Washington Counties, Idaho
project featured image

Bathymetric Surveying

Multiple States
project featured image

Dam Monitoring

Multiple States
project featured image

BYU-Idaho, Central Quad

Rexburg, Idaho
project featured image

Gem County Engineer

Gem County, Idaho

Challenged by explosive growth and the creation of a new resort community (Tamarack), the North Lake Recreational Sewer and Water District worked closely with Keller Associates in developing a treatment system that would meet the growing needs of a pristine recreational area.

Cost: $15,700,000
Services Provided:
  • Keller Associates completed the quick-paced master planning and design services and provided construction support services through plant startup
Project Features:
  • 1.25 MGD treatment plant entirely enclosed in a steel building to look like a rural area horse barn
  • 45-foot-high steel building and frame used to support snow and wind loads and a multi-ton crane that moves throughout the building
  • Masonry enclosures were used to isolate machinery and dampen noise
  • Plant houses large concrete MBR tanks over 20 feet deep extending below the floor
  • Complex concrete structures with multi-levels of suspended concrete work
  • Moment framing was incorporated to provide unobstructed areas to house equipment and storage and allow open work areas and office space