Potable Water System Master Planning and Implementation
City of Ontario, Oregon

OVERVIEW
Keller Associates developed a complete GIS system for all of the City’s potable water, sanitary sewer, and storm sewer facilities. Utilizing this GIS database, comprehensive detailed utility master plans were then developed for each of these utilities. Our services included implementation of the key elements of the potable water system master plan, including (1) a 3.0 MG steel reservoir located on the bench northwest of town to provide gravity flow to the City; (2) conversion of two pressure zones to one pressure zone, (3) 2.5 miles of 24-inch transmission pipelines, (4) miscellaneous distribution system pipelines, and (5) a new 4.0 MGD water filtration plant. Keller also designed a SCADA control facility to operate three major booster pumping facilities from the new 3.0 MG bench reservoir.

 

CHALLENGE
Over half the water used in the City of Ontario goes to the Heinz Food Processing plant, which requires a continuous uninterrupted water supply (5.12 MGD). The State Correctional Facility also expanded to over 3,000 beds, requiring an additional 0.8 MGD of potable water. The existing plant was rated at 8.0 MGD, but on some peak summer days was required to process up 10.5 MGD. The existing facility draws raw water from the Snake River, which is contaminated with extremely high sediment during spring runoff and high concentrations of algae in late summer.

SOLUTION
Through the master planning process, Keller Associates developed unique concept solutions addressing each of the City’s potable water system challenges. Keller Associates was subsequently retained to design and implement each of the concepts. The lack of potable water filtration treatment capacity and the periodic poor raw water quality from the Snake River was resolved with construction of a new parallel 4.0 MGD water filtration plant and a new raw water intake facility that collects and conveys raw water from a nearby abandoned gravel pit pond. The uninterrupted water supply pressure problems and controls were resolved with construction of the new 3.0 MG bench reservoir and transmission pipelines direct to the City and Heinz Foods processing plant. All facilities are controlled by a new SCADA control system operated from the new bench reservoir, thus eliminating the need for two separate pressure zones.
Ontario Water System
Chubbuck Water System
Nampa Water System
 

• GPS control and utility location
• Planimetric feature aerial mapping
• Citywide GIS development
• Potable water system master planning
• Extensive computer modeling
• Pre-design reports
• Preparation of final plans and specifications
• Bidding services
• Easement preparation and utility locations
• Construction engineering services
• Inspection
• Final start-up and acceptance
• One-year warranty review and acceptance

Keller Associates, Inc. © 2008